Author Notes
The SPARC tokamak is a high-field, Bt0 ∼12 T, medium-sized, R0 = 1.85 m, tokamak that is presently under construction in Devens, MA, led by Commonwealth Fusion Systems. It will be used to de-risk the high-field tokamak path to a fusion power plant and demonstrate the commercial viability of fusion energy. SPARC’s first campaign plan is to achieve Qfus > 1 using an ICRF-heated, <10 MW, high current, Ip ∼ 8.5 MA, L-mode fueled by D–T gas injection, and its second campaign will investigate H-mode operations in D–D. To facilitate plasma control and scientific learning, a targeted set of ∼50 plasma diagnostics are being designed and built for operation during these campaigns. While nearly all diagnostics are based on established techniques, the pace of deployment, relative to the first plasma, and the harshness of the thermal, electromagnetic, and radiation environment are unprecedented for medium-sized tokamaks. An overview of the SPARC diagnostic set is given, providing context to further details communicated by the SPARC team in companion publications that are system-specific. The system engineering philosophy for SPARC diagnostics is outlined, and the design and engineering verification process for components inside and outside the primary vacuum boundary are described. Diagnostics are mounted directly to the vacuum vessel as well as housed within a series of eight midplane and 24 off-midplane replaceable port plugs. With limited exceptions, signal conditioning, digitization electronics and cameras as well as lasers and microwave sources are localized to a series of five Diagnostic Lab spaces, totaling ∼350 m2, located >15 m from the center of the tokamak, on the other side of a 2.4 m concrete shielding wall. A series of 31 large-scale penetrations have been included in the SPARC Tokamak Hall to facilitate integration of early campaign diagnostics and to provide upgradability.
I. INTRODUCTION
Commonwealth Fusion Systems (CFS) is a private company, founded in 2018, spun out of the MIT Plasma Science and Fusion Center. The mission of CFS is to fast-track the commercialization of fusion energy on a timescale that can mitigate climate change by innovating high temperature superconductor (HTS) based, high-field magnets1 and leveraging decades of scientific progress in understanding compact, high-field tokamaks.2 The SPARC tokamak3 is presently under construction in Devens, MA, and will be used by scientists and engineers to answer key open questions to inform the design of the ARC power plant, early concepts of which are discussed in Refs. 4 and 5.
The motivation and need for plasma diagnostics in a commercial fusion R&D facility such as SPARC are different from both a publicly funded facility, whose mission is to support a wide scientific user base, and a commercial power-plant, whose goal is to cost-effectively generate electricity. Plasma diagnostics are needed for real-time control as well as to make the inter-shot observations necessary to advance a scientific mission. As the focus shifts from a user facility to a power plant, what evolves is the ratio of diagnostics used to satisfy each of these needs. SPARC is positioned in the middle of that evolution, with nearly all diagnostic systems having some role in real-time or plant-level control while also being leveraged to close plasma physics gaps. Some of the design decisions and approaches are inherent to its one-off, R&D role and, as such, may not make sense for neither a user facility nor a power plant.
Construction of the SPARC facility is led by CFS using funding provided by private investment, but the SPARC team is multi-institutional, with, at present, contributions from close to 1000 people from over 20 institutions. The fast development timeline and limited resources of the SPARC project created a need to use demonstrated, high-TRL approaches to measure the plasma. Our approach leverages private–public partnerships, building a SPARC diagnostic team that combines people with deep fusion community heritage with those that have experience outside of fusion and adds a diverse set of engineering, design, supply-chain, manufacturing, and assembly skill sets. While specific sub-components and materials require innovation and prototyping, the basic diagnostic techniques used on SPARC have been repeatedly demonstrated on previous tokamaks. In contrast to large bore, HTS magnets, which required new test stands to demonstrate,6 and for CFS to build a dedicated factory to fabricate them, SPARC diagnostic proof-of-concepts and integrated tests occurred over decades of government-sponsored research on fusion facilities around the world.7
The need for another step-change improvement in plasma diagnostics to support real-time control of ARC is acknowledged and has been discussed in scoping studies for devices such as DEMO.8 It is not a mission of SPARC’s diagnostics to demonstrate the specific diagnostic technology that enables ARC operation. Instead, it is to identify the requirements that bound a minimum viable measurement set for a power plant. The scope of this article is focused on the diagnostics that the SPARC diagnostic team is designing and building for Campaign #1 and Campaign #2. The focus of campaign #1 will be integrated commissioning in H2, 4He, and D2 plasmas, leading to a demonstration of a high-current, D–T fueled, ICRF-heated L-mode plasma, which is estimated to reach Qfus > 1.9 Campaign #2 will focus on demonstrating enhanced confinement regimes in D–D. Starting in Campaign #3, the diagnostics will be used in high power D–T scenarios, which aim to target Qfus ∼11. Many of the diagnostics are designed to operate over SPARC’s full lifetime and need to be deployed and/or commissioned within the first two campaigns. The SPARC operational parameters of the Campaign #1 Qfus > 1 L-mode (Q1L) and the Campaign #3 Qfus ∼11 Primary Reference Discharge (PRD) are outlined in Table I.
SPARC parameters for the Qfus ∼ 11 primary reference discharge (PRD) and first campaign Qfus > 1L-mode (Q1L). Both have Ro = 1.85 m and a = 0.57 m, and assume nD = nT.
Parameter . | Units . | PRD . | Q1L . |
---|---|---|---|
Plasma current, Ip | MA | 8.7 | 8.5 |
Toroidal field | T | 12.2 | 12.2 |
Elongation, κa | 1.75 | 1.70 | |
Normalized confinement | H98 ∼ 1.0 | H89 ∼ 1.0 | |
Magnetic geometry | DN | SN | |
Δt flattop | S | 10 | 4.0 |
τE | s | 0.77 | 0.56 |
Ohmic power | MW | 1.7 | 5.8 |
ICRF heating | MW | 11.1 | 2.8 |
Fusion power | MW | 140 | 9.5 |
⟨Te⟩ | keV | 7.3 | 5.8 |
⟨ne⟩ | 1020 m−3 | 3.1 | 1.1 |
Zeff | 1.5 | 2.9 | |
Wpl | MJ | 22.3 | 5.8 |
Parameter . | Units . | PRD . | Q1L . |
---|---|---|---|
Plasma current, Ip | MA | 8.7 | 8.5 |
Toroidal field | T | 12.2 | 12.2 |
Elongation, κa | 1.75 | 1.70 | |
Normalized confinement | H98 ∼ 1.0 | H89 ∼ 1.0 | |
Magnetic geometry | DN | SN | |
Δt flattop | S | 10 | 4.0 |
τE | s | 0.77 | 0.56 |
Ohmic power | MW | 1.7 | 5.8 |
ICRF heating | MW | 11.1 | 2.8 |
Fusion power | MW | 140 | 9.5 |
⟨Te⟩ | keV | 7.3 | 5.8 |
⟨ne⟩ | 1020 m−3 | 3.1 | 1.1 |
Zeff | 1.5 | 2.9 | |
Wpl | MJ | 22.3 | 5.8 |
A primary purpose of this article is to communicate details of the planned SPARC plasma diagnostics to two audiences. The first is potential scientific users of SPARC, where this document provides the top-level details of what measurements SPARC will have and why. Through references and future citations, this will act as an index to publications that have more granular details. The second audience is those interested in designing future diagnostics for SPARC. The details provided should allow rough, conceptual scoping as to whether a new diagnostic would be feasible and could be integrated into the SPARC facility. This article is broken down as follows: In Sec. II, the major design constraints are outlined. Cross sections of the vacuum vessel, Tokamak Hall, and Diagnostic Labs are given to highlight what limits diagnostics being integrated into the vessel and facility spaces. Section III summarizes the top-level performance and functional requirements that the diagnostic systems meet and shows how these are mapped to the specific instrument sub-systems, with details in the supplementary material associated with this article. Also presented is a schematic layout for how the limited spaces have been apportioned to various diagnostics. Sections IV and V outline the design philosophy, challenges, and opportunities for future enhancement of in-vessel and port-based diagnostics. Section VI expands on the capabilities and design within the Diagnostics Labs, and Sec. VII provides a brief summary.
II. MAJOR DESIGN CONSTRAINTS
More details on the overall design of the SPARC tokamak can be found in Ref. 3, and Table I highlights some of the engineering and plasma parameters relevant to diagnostics. This section focuses on outlining major constraints that bound diagnostic design, some of which will be installed after the initial assembly over the 13 000 pulse, 10-year lifetime of SPARC. At R = 1.85 m, a = 0.57 m SPARC is the size of existing medium-sized, cryostat encapsulated tokamaks such as KSTAR10 that have superconducting coils. This size similarity enables the transfer of know-how and technology from proven diagnostics, where features are constrained by geometry. The key distinguishing characteristic of SPARC is the use of HTS magnets, which allow the on-axis field to reach 12.2 T and currents up to 8.7 MA. Despite having HTS coils, SPARC is a pulsed device with Δtflat ∼ 10s.
SPARC is built on a green-field site, and the basic sizing and layout of the facility were completed, while the diagnostic systems were in the early conceptual design. Most of the detailed designs of the diagnostic systems have proceeded with these features as boundary conditions rather than trying to simultaneously optimize the two. This approach has facilitated the speed of deployment for SPARC without encountering significant restrictions. Figure 1 shows a recent photograph of the Tokamak Hall, along with a top–down schematic. No diagnostic equipment is shown, with the goal of this section to outline the large-scale interfaces that constrain instrument design.
Layout and sizing of the SPARC Tokamak Hall and positioning of the Diagnostic Labs to the east of the cryostat.
Layout and sizing of the SPARC Tokamak Hall and positioning of the Diagnostic Labs to the east of the cryostat.
The SPARC cryostat, R ∼ 4.6 m, sits in the center of the Tokamak Hall with the midplane at Z ∼ 5.0 m above the floor and total height of ∼9.2 m. Diagnostics interface in two key ways, through the 18 rectangular slots in the floor near the center of the device and through 33 penetrations in the 2.4 m thick east wall. These are labeled in Fig. 2, along with the layout of five Diagnostic Labs, which will house equipment that cannot survive high neutron fluxes, up to ∼1 × 1011 n/cm2/s, estimated in the Tokamak Hall for the 140 MW Primary Reference Discharge (PRD). Wired connections from sensors in the tokamak go into the basement and either proceed directly to the Diagnostic Labs through east/west running cable tray or sent to analog front-end electronics (integrators, trans-impedance amplifiers) and then routed to the Diagnostic Labs. Teal colored vertical and east/west cable tray distribute the signals to signal conditioning and digitization electronics in the two floors of the Diagnostic Labs. Cable runs of 30–40 m are within distances that have been shown to work on existing tokamaks.
Layout and sizing of the Diagnostic Labs and early campaign utilization of the Diagnostic Hall Penetrations.
Layout and sizing of the Diagnostic Labs and early campaign utilization of the Diagnostic Hall Penetrations.
Four of the Lab spaces are of similar size, 9.0 × 8.2 m2, and will house equipment that uses 24 of the 1.22 × 1.22 m2 penetrations. The upper north (UN) and upper south (US) labs also have a 20 cm diameter circular penetration (NLOS, SLOS) that points to the core of the plasma. The ground-level, lower north (LN), and lower south (LS) are being used for equipment that may benefit from having the shortest cable runs as well as equipment that may require more stable mounting surfaces. The central lab space is taller and narrower and was designed specifically with neutron and gamma imaging in mind. The six larger penetrations (NC1–NC6) are 1.22 × 2.13 m2, along with vertically extended 0.61 m wide penetration for poloidal imaging (NC0). These penetrations have been roughly allocated to different measurement systems, shown in Fig. 2, with labels referencing system names in Table II. Most of the void space in the penetrations will be refilled with shielding, as they were designed to be oversized in order to allow for future optionality and upgradability. This toroidally non-uniform layout of the Diagnostic Labs relative to the tokamak creates a pattern of utilization for the port-plugs that is evident in their layout discussed in Sec. III.
List of SPARC early campaign diagnostics.
Diagnostic . | Label . | Early campaign scope . |
---|---|---|
Magnetic diagnostics | MAGX | Flux loops, Ip Rogowski, Bx sensors, halo Rogowskis, high frequency Mirnovs |
Interferometry and polarimetry | INPL | Single chord, two-color interferometer |
Neutral gas diagnostics | NTGS | Main-chamber + divertor neutral pressure and RGA |
UV/Vis/IR imaging | IMAG | Multiple divertor, main-chamber, and antenna imaging views |
X-ray diagnostics | XRAY | Hard x-ray, soft x-ray imaging, and high- and low-resolution crystal spectroscopy |
UV/Vis/IR spectroscopy | SPEC | Filterscopes, bremsstrahlung, H/D/T and 3He/4He isotope ratios, divertor, and main chamber grating spectroscopy |
Vacuum spectroscopy | VCSP | Core and divertor impurity spectroscopy |
Bolometers | BOLO | Divertor, core, and disruption radiated power |
Thermal sensing | THRM | Embedded thermocouples, FBGs, surface thermocouples in main-chamber + divertor |
Neutron diagnostics | NTRN | Flux monitors, foil activation, poloidal imaging camera, core magnetic recoil spectrometer |
Thomson scattering | TSCT | Low-resolution core profile measurement |
Millimeter wave diagnostics | MMWV | Electron cyclotron emission, edge scanning reflectometer |
Langmuir probes | LANG | Divertor and main-chamber probes, current shunts |
Displacement sensing | DISP | Vacuum vessel and coil displacement sensors |
Strain sensing | STRN | Vacuum vessel strain sensors |
Diagnostic . | Label . | Early campaign scope . |
---|---|---|
Magnetic diagnostics | MAGX | Flux loops, Ip Rogowski, Bx sensors, halo Rogowskis, high frequency Mirnovs |
Interferometry and polarimetry | INPL | Single chord, two-color interferometer |
Neutral gas diagnostics | NTGS | Main-chamber + divertor neutral pressure and RGA |
UV/Vis/IR imaging | IMAG | Multiple divertor, main-chamber, and antenna imaging views |
X-ray diagnostics | XRAY | Hard x-ray, soft x-ray imaging, and high- and low-resolution crystal spectroscopy |
UV/Vis/IR spectroscopy | SPEC | Filterscopes, bremsstrahlung, H/D/T and 3He/4He isotope ratios, divertor, and main chamber grating spectroscopy |
Vacuum spectroscopy | VCSP | Core and divertor impurity spectroscopy |
Bolometers | BOLO | Divertor, core, and disruption radiated power |
Thermal sensing | THRM | Embedded thermocouples, FBGs, surface thermocouples in main-chamber + divertor |
Neutron diagnostics | NTRN | Flux monitors, foil activation, poloidal imaging camera, core magnetic recoil spectrometer |
Thomson scattering | TSCT | Low-resolution core profile measurement |
Millimeter wave diagnostics | MMWV | Electron cyclotron emission, edge scanning reflectometer |
Langmuir probes | LANG | Divertor and main-chamber probes, current shunts |
Displacement sensing | DISP | Vacuum vessel and coil displacement sensors |
Strain sensing | STRN | Vacuum vessel strain sensors |
Another key interfacing limit for the diagnostics is the size layout of the SPARC vacuum vessel (VV) and in-vessel components. This is highlighted in Fig. 3 with sizing indicated to help orient readers. Section IV and Fig. 4 provide further detail related to sub-divertor diagnostics. The nominal size, shape, and features of the VV, including the port plug locations, were locked early in the SPARC design, driven by non-diagnostic interface constraints. SPARC is fully up/down symmetric, which increases sensor count, and lacks any vertical ports, which constrains a number of typical diagnostic approaches. There are 18 midplane port (MP) openings and 16 upper off-midplane and 16 lower off-midplane port (OMP) openings, though not all are filled with removable port plugs. Of the ∼5100 diagnostic electrical pins that exit the primary vacuum boundary, ∼3100 do so at 24 dedicated feedthrough sub-assemblies located above (below) the upper (lower) off-midplane port plugs, as identified in Fig. 3. This allows off-midplane port plugs to be exchanged without disturbing in-vessel diagnostic cabling.
Layout of SPARC vacuum vessel, port-extensions, and major in-vessel components. The toroidal width of the port-extensions is 0.550 and 0.375 m for the midplane and off-midplane, respectively.
Layout of SPARC vacuum vessel, port-extensions, and major in-vessel components. The toroidal width of the port-extensions is 0.550 and 0.375 m for the midplane and off-midplane, respectively.
Layout of SPARC’s wired, in-vessel diagnostics (INVD). Sub-system labels are outlined in Table II.
Layout of SPARC’s wired, in-vessel diagnostics (INVD). Sub-system labels are outlined in Table II.
Cooling of the diagnostics is accomplished primarily by circulating room-temperature He gas between the two shells of the VV and using conduction to transfer heat to the VV. This circuit is also used for baking SPARC, which can go up to 350 °C. Liquid cooling of any kind was restricted by top-level requirements, and circulating gas cooling to discrete diagnostic components was avoided by choice. Some heat rejection via radiation to the cryostat thermal shield can occur for large major radius portions of the port extensions. This limited cooling eases design and integration in-vessel, but results in the temperature of the VV, PFCs, and diagnostic components ratcheting up over an 8 h run day. This ratcheting increases for components with larger conduction paths to the VV surface. Estimates from global thermal modeling indicate that a 4 h inter-pulse cooldown is necessary for the PRD, while a full power, full-length D–D plasma requires nominally 40 min. SPARC systems, including diagnostics, are designed to be able to support an inter-pulse time of 20 min in cases where injected or generated energy is limited. This facilitates fast learning early in SPARC’s operational life.
The ability to observe emission from the plasma is a key requirement for many diagnostics, which is moderated by the plasma-facing components. The PFC contour is available on-line in Ref. 11. Poloidally, between the two OMPs, the PFC contour is toroidally discontinuous, with SPARC having 18 rail-style limiters (OLIM). With limited exceptions away from high-heat flux zones, discussed in Sec. IV, the PFCs are then toroidally continuous everywhere else. Areas in the main-chamber where there are no PFCs may have an excellent view, but are also outside of the protection PFCs provide. Having 18 limiters results in relatively short toroidal connection lengths, <1 m, between PFC surfaces. Parallel conduction competes with cross-field transport to reduce the radial scale length of the far scrape-off layer and electron + ion heat flux to spaces between limiters. The charge-exchange and photon fluxes remain high for many plasma-viewing diagnostic components if left unshielded. Ray tracing estimates using HEAT12 show that the front of port plugs will see 10–15 kW/m2 for every MW of radiated power from the core. This corresponds to a heat flash of 0.32–0.47 MJ/m2/s1/2 for every MJ of core stored energy if released over a 1 ms thermal quench timescale. For the PRD, thermal heating from neutrons is ∼10 MW/m3 for steel used by diagnostics for mounting to VV, PFCs, and port-plugs. Due to the pulsed, low duty factor D–T operation, nuclear heating does not play a significant role in limiting design in contrast to surface heating from radiated power in D–D plasmas.
Surviving disruptions is a key challenge for diagnostic components inside the SPARC TF field. Survival is defined by the SPARC Structural Design Criteria (SDC), which draws from the ASME Boiler and Pressure Vessel Code and the TPX SDC.13 For many metallic components, the criterion which limits the size of diagnostic components is to keep primary stresses below 2/3 of the yield stress, at temperature, to avoid plastic collapse. Components are additionally analyzed for local failure and fatigue. Transient, spatially varying volumetric force densities are calculated using an in-house workflow starting with ANSYS Workbench and Mechanical APDL scripting. Induced 3D currents are modeled in a Δϕ = 20° sector of the tokamak with cyclically coupled boundary conditions. The dynamics of the plasma are represented by 193 current filaments, with two different scenarios, a vertical displacement event (VDE) and major disruption (MD). In the VDE scenario, the vertical position drifts exponentially, moving 0.6 m over 120 ms. The plasma cross section shrinks, keeping the total current fixed until the edge safety factor reaches unity at which the current decays. In a major disruption, the plasma current decays at its centered position in the vacuum chamber. Both scenarios decay the total current exponentially as , a rate of decay that is derived from the ITPA disruption database scaling.14 That work compiled cross-machine current quench data, and SPARC has chosen a value of Δt80−20 = 3.2 ms, based on assuming that all SPARC disruptions will occur at Δt80−20/S > 2.0 ms/m2. For context setting, this results in dBz/dt at the outboard midplane, where Bp = 2.8 T, to be more than 2000 T/s at the initiation of the current quench. The resulting eddy currents induced in the vacuum vessel, nearby in-vessel structures, and diagnostic components combine to create Lorentz body forces in objects, where the large toroidal field of SPARC further contributes on top of the high dBp/dt. These loads are used as inputs into ANSYS structural simulations to compute stresses and compare to allowables. Since materials (e.g., strength, resistivity) and physical scale are similar to other medium sized tokamaks, SPARC’s increase in BT at similar desired range of q∗ results in forces within diagnostic components that grow nominally quadratically with toroidal field compared to devices such as KSTAR, EAST, AUG, and DIII-D. Using XM-19 instead of 316 stainless steel is a common tool to increase margin to allowable, but generally, SPARC diagnostic components end up reducing in size or increasing in fabrication complexity to include features for eddy current suppression. The ANSYS workflow can also account for halo currents, but in general, this is not a design driver for diagnostics. In the Tokamak Hall, dead-load and seismic loads are the primary structural design concerns and are independent of SPARC’s compact, high-field approach relative to other tokamaks. SPARC’s high current operation does result in increased residual poloidal magnetic fields outside of the cryostat, roughly 500 G at ∼10 m from the center of the tokamak, at the midplane, and still above 20 G at the far end of the Diagnostic Labs. This increases the variety of components that need magnetic shielding in comparison to other medium-sized tokamaks. Error field studies show that within the Tokamak Hall at roughly 6 m < R < 12 m, ∼10 kg of high permeability material should not create a negative impact on SPARC. Outside of 12 m, error field considerations do not restrict the mass of magnetic shielding material.
III. REQUIREMENTS AND SYSTEM LAYOUT
The scope of diagnostics for SPARC was outlined in mid-2020, in parallel with the early engineering design of the larger structures and interfaces such as the vacuum vessel, PFCs, port-plugs, and in-vessel coils. The top-level general requirements that bound the diagnostics were that they support tokamak operations in achieving the primary reference discharge and provide sufficient information to validate three primary missions: (a) demonstrate net fusion energy (Qfus >1) and high gain (Qfus ∼ 11), (b) demonstrate divertor solutions for the ARC design, and (c) retire broader ARC physics risks. While all are more broadly defined in internal mission statements, there still was substantial room for interpretation of what precisely needed to be measured and why. To avoid a lengthy and costly concept of operations study early in the project, an approach was taken to leverage existing tokamak community knowledge and high-TRL demonstrations to identify the likely measurement classes that SPARC would inevitably need.
This consisted of a down-selection from existing, proven techniques using surveys of complete diagnostic sets on ITER and existing devices, along with a prioritization relative to SPARC’s mission goals. This resulted in 67 Level 3 (L3) instrumentation sub-systems in the SPARC product breakdown structure, where diagnostics (DIAG) is a Level 1 (L1) system. The goal of the SPARC diagnostic team is to pursue 45 of these for early campaigns. These are summarized in Table II at the Level 2 (L2) system level, which collects L3 sub-systems by technology and design challenge. Some diagnostics were excluded due to the lack of supporting auxiliary systems, such as neutral beams, and others excluded by risk avoidance, such as scanning probes and retractable material exposure stations. There are additional sub-systems being developed to facilitate cross-system measurements, such as electrical and fiber feedthroughs, support platforms, and radiation shielding, none of which are listed in Table II. Additionally, the wider SPARC team is developing more instrumentation for magnet and plant system control that is beyond the scope of this article. The focus of the diagnostics is on making measurements of the plasma itself or sensing the impact of plasma-driven effects on the environment, such as thermal effects and electromagnetic forces from disruptions.
Even with measurement classes identified, further identification of the function and purpose of the diagnostics were required to bound design. Quantitative requirements at the L1 system level were intentionally avoided to not create a situation where conservative physics assumptions would drive design churn. The list of sub-systems was further mapped into five tiers to help prioritize the schedule and need.
Tier 1A: needed for the first plasma and basic operation.
Tier 1B: needed for high power and high current operations.
Tier 2A: needed to achieve net fusion energy mission.
Tier 2B: needed to achieve the divertor mission.
Tier 2C: needed to achieve the ARC physics mission.
General requirement statements were then developed by internal stakeholders and reviewed in early 2021 and have nominally remained unchanged since then. These typically take the form of “DIAG shall measure or infer <some property/component> for the purposes of <some function/need>”. For example, “DIAG shall measure or infer the temperature of the plasma-facing components for the purpose of preventing damage” is a Tier 1B requirement and “DIAG shall measure the D–T ratio for the purpose of controlling fusion power” is a Tier 2A requirement. In total, there are 26 Tier 1A, 20 Tier 2B, 10 Tier 2A, 16 Tier 2B, and 7 Tier 2C requirements. These requirements were then mapped, some non-exclusively, to the L2 system listed in Table II based on prior examples in tokamaks. The full list is shown in the supplementary material. The process of conceptual and early preliminary design over 2021–2023 was to clarify these requirements into quantitative statements at the L2 or L3 system level that would then drive design. This facilitated early iterations where requirements were bound or adjusted by what was estimated to be feasible within the constraints of SPARC’s engineering loads or resource limits. Being able to downgrade performance requirements or defer portions of a sub-system was key in maintaining early progress by avoiding “desirements” (i.e., desires disguised as requirements) from research end-users driving substantial design churn or cost-escalation. This system-engineering approach is somewhat non-standard for the ground-up development of a ∼B$ science facility, but is generally reflective of how contemporary diagnostic deployment is the “art of the possible” and consistent with the unique nature of the SPARC mission and team, highlighted in Sec. I.
In addition to time, material limits, and cost, physical space is also a resource that impacts the SPARC diagnostic design. SPARC being compact and high-field exacerbates this due to a smaller area to observe the plasma and a greater need for a fraction of that to be steel for structural support. The requirement to run in D-T necessitates space be given to B4C neutron shielding inside the primary vacuum boundary and to minimize approaches that require large, direct lines of sight. Figures 4 and 5 show a schematic layout of how this space has been apportioned between diagnostics and other systems. Figure 4 shows the wire-ways and space reservations used to route cables from sensors mounted to the vacuum vessel to electrical and fiber feedthroughs. More details on the philosophy, challenges, and enhancement opportunities are discussed in Sec. IV. The block diagram in Fig. 5 shows how the 18 midplane and 36 off-midplane port spaces are broken down between diagnostics, listed in Table II, and other systems. Note that ESRL and ECE are MMWV sub-systems and FOIL, NCAM, and NSPC are NTRN sub-systems. More details are discussed in Sec. V.
Layout of and use of SPARC’s upper (UP) and lower (LP) off-midplane and midplane (MP) port plugs. The view is from the inside of the vacuum vessel looking outward. The included table provides an index of non-diagnostic systems referenced in the figure. Table II provides an index for diagnostics systems.
Layout of and use of SPARC’s upper (UP) and lower (LP) off-midplane and midplane (MP) port plugs. The view is from the inside of the vacuum vessel looking outward. The included table provides an index of non-diagnostic systems referenced in the figure. Table II provides an index for diagnostics systems.
The ability to upgrade portions of the diagnostic system over time as well as some of the uncertainties in what SPARC might may encounter have resulted in a prioritization of resources that continuously impacts the on-going design. Resources, especially time, are finite in a mission-driven project such as SPARC. The priorities, in order, are for the diagnostic system (a) to be able to control plasmas needed in Campaign #1 while being resilient to a limited range of physics and technology risks, (b) to make a reliable Qfus > 1 measurement, (c) to deploy redundancy for diagnostics that will be difficult to maintain after initial assembly and low-level activation, and (d) to deploy measurements needed in Campaign #2 that need to be commissioned using Campaign #1 plasmas and be resilient to a broader range of Campaign #1 and Campaign #2 physics and technology risks.
IV. IN-VESSEL DIAGNOSTIC DESIGN
For SPARC, in-vessel diagnostics refer to the class of sensors that are inside the vacuum vessel or exist between the vacuum vessel and cryostat and have distinct challenges from diagnostics that are built into port-plugs, discussed in Sec. V. This section focuses on sensors on the plasma-side of the vacuum vessel from magnetics (MAGX),15 neutral pressure sensors (NTGS),16 bolometry (BOLO),17 thermal sensors (THRM),18 and Langmuir probes (LANG). Two Rogowski coils (MAGX), 44 thermocouples (THRM), as well as the entirety of the displacement (DISP) and strain (STRN) sub-systems are within the cryostat vacuum and outside of the scope of this article.
Figure 6 provides a zoomed-in view of Fig. 3, highlighting the in-vessel components that diagnostics need to design around. The PFC contour is displaced from the VV by discrete pedestals at 36 toroidal locations per poloidal sector, which creates a set of poloidally running “highways.” A poloidally continuous gap of at least 3 cm wide is ensured from the inner limiter (ILIM) to the off-midplane port. At its narrowest, there is space only for MgO-based mineral insulated cables (MICs), fused silica fiber optic cables, and gas fueling lines (FINJ). In zones behind the inner off-midplane limiter (IOLIM) and outer off-midplane limiter (OOLIM), which define the divertor throat and the divertor tiles (T1 → T6), there is room for larger discrete sensors and even pinhole cameras (BOLO). As much as feasible, toroidally extended cable runs are avoided so that cables can exit the vacuum boundary at the same toroidal location. Poloidal flux measurements are made mostly using Δϕ = 40° partial flux loops, with only eight full flux loops installed in locations of extended poloidal gaps between PFC support structures. The presence of the four-turn vertical stability coils above and below the midplane port opening restricts routing in the region between the upper and lower OOLIM. Support structures for RF antennas and outer limiter (OLIM) also restrict space for sensor mounting compared to other medium-sized and small tokamaks. Of the few in-vessel sensors that exist in this zone, many exit the primary vacuum boundary at ports that are not externally replaceable, such as those that have ICRF antennas, those where in-vessel coil leads exit, or the torus pumping port (see Fig. 4 or 5). All MICs are hermetically sealed to limit out-gassing and low-voltage (1 A, 500 V), high-current (10 A, 500 V), high-voltage (1 A, 5000 V), as well as fiber-optic feedthroughs have a secondary space to mitigate the impact of leaks and tritium permeation. Pre-amplifier and back-end electronics for in-vessel sensors are grouped into six grounding zones, shown in Fig. 5, to avoid needing high channel-to-channel isolation from disruption induced voltages, with Vloop > 1.0 kV at the inner midplane.
Layout of SPARC vacuum vessel, port-extensions, and major in-vessel components. PFCs that use pure-W are shown in orange, while PFCs that use the tungsten heavy alloy are shown in purple. Dedicated baffling (not shown) directs neutrals down the port-extension.
Layout of SPARC vacuum vessel, port-extensions, and major in-vessel components. PFCs that use pure-W are shown in orange, while PFCs that use the tungsten heavy alloy are shown in purple. Dedicated baffling (not shown) directs neutrals down the port-extension.
Due to the high heat fluxes expected on SPARC divertor plasma-facing components,19 multiple restrictions were put on interfacing diagnostics. In areas where pure-W is used (T1, T2, T4, T5b, T6, and OLIM), no top-surface holes are allowed, so there are no Langmuir probes or surface thermocouples (STCs) anywhere that a primary strike point would be located for a single null (SN) or double null (DN) equilibrium. To avoid introducing stress concentrations in the pure-W, thermocouples are limited to the non-plasma-facing side of the tungsten material and the interfacing steel mounting structures. Toroidal gaps between pure-W tiles were minimized, and no dedicated gaps for plasma viewing diagnostics are accommodated as this would have created the need to locally enhance the fish-scale angle of the tiles and create a “weak spot” in the divertor armor. Toroidally extended gaps are allowed where PFCs used tungsten heavy alloy (WHA) and were used to enable divertor views for BOLO. Dedicated gaps at four toroidal locations for divertor neutral pumping also allow for a view of the x-point target chamber, which is formed by T5a, T5b, T5c, and T5d, and the gap between T4 and T6. The vertically extended T5c surface is a WHA tile, which allows for STC and Langmuir probes to be installed, and this surface will be the landing point for strike points in an x-point target geometry.20
The main environmental challenges that in-vessel diagnostic sensors face are high temperatures from bake and electromagnetic loads from vertical displacement event disruptions. VV-mounted sensors are generally shielded from the line-of-sight view of the plasma and nuclear heating is limited, 16–17 W/cm3 in steel directly seeing the plasma and an order of magnitude lower behind PFCs, while also having the shortest path to the actively cooled surface. This makes qualifying sub-assemblies to survive bake, nominally set at 400 °C, as the critical thermal limit, while material properties for surviving disruption are set at the 150 °C max operating temperature of the VV. Restrictions on materials for compatibility with tritium processing equipment and to limit activation can also challenge design. No sulfide-based lubricants (e.g., MoS2) or halogen-containing materials are allowed. Although they are ideal for high-temperature, high-strength applications, there is no large-scale use of Ni-rich alloys in order to reduce activation. High-activation materials are limited to few kg-levels across diagnostics, used in small-scale components, such as springs, pins, or coatings.
The VDE scenario described in Sec. II is the main structural design driver for qualifying diagnostic sensors and cable tie-downs mounted to the vacuum vessel. These are a combination of loads generated by the eddy currents in the component itself due to local dBp/dt, bending stresses imposed by the vacuum vessel for poloidally extended diagnostics, and a moment about the normal of any sensor that is electrically connected to the vessel. In the latter, a fraction of the toroidally running currents in the vessel will follow a path radially in/out of a diagnostic component to produce this torque. For the same reason, poloidally running halo current may also run through the diagnostic, but this creates a force that compresses the sensor against the vessel and is not challenging to manage. The primary means that diagnostics use to react these loads is studs welded to the VV. Inertial loads from the vertical force are not meaningful due to the limited mass of sensors and the large eddy current loads.
The other main challenge for in-vessel diagnostics is designing and qualifying components, assuming that there is no in-vessel, sub-divertor maintenance. SPARC’s mission and operational plan is designed to allow for a single in-vessel entry after Campaign #2. The extent of removal of in-vessel components is expected to be limited to only tiles and not removing their support plates, which would allow access to the “highways” and most of MAGX, NTGS, BOLO, THRM, and LANG. This motivates including redundancy as well as using sensors with different potential failure modes to create defense in depth. While completion of the divertor mission is not planned to happen by the end of Campaign #2, many diagnostics that are required to achieve that mission need to be installed for the first plasma. Diagnostics that rely on fiber-optic cables may not survive the full lifetime of SPARC, though testing at SPARC fluence levels shows radiation induced attenuation having a significant temperature and wavelength dependence.21 Those that use NIR, such as fiber-Bragg gratings or hydrogen Paschen series, have a much greater chance than UV/visible. The SPARC team will pursue and test optical annealing as well to help extend lifetimes.
V. PORT-BASED DIAGNOSTIC DESIGN
For SPARC, the port-based diagnostics refer to the class of sensors that are mounted to replaceable port-plugs. This restricts their ability to view the plasma but creates the possibility for upgrades. As shown in Fig. 5, interferometry (INPL),22 neutral pressure sensors (NTGSs),16 UV/visible/IR imaging (IMAG), X-ray spectroscopy (XRAY),23 vacuum ultraviolet spectroscopy (VCSP),24 bolometry (BOLO),17 Thomson scattering (TSCT), and millimeter wave (MMWV)25 all have major components occupying portions of port-plugs. Mirnov arrays (MAGX) are also included, while thermal sensing (THRM)18 monitors the temperature of multiple port-plugs, and IMAG plans to include multiple fibers to be used to back-light for inter-shot inspection. CFS does not have a hot-cell at the SPARC facility for extraction, maintenance, and re-installation of the first generation of port plugs. Features that are accessible from inside the assembled tokamak may be adjustable during the post-Campaign #2 entry if critical, but the baseline maintenance strategy for in-vacuum components is “no maintenance.”
The primary functions of the port-plugs are to (1) ensure the integrity of the primary vacuum boundary, (2) assist in reducing the neutron flux to allowable levels for the HTS coils and Tokamak Hall, and (3) provide a flexible, adaptable mounting structure for client systems, such as diagnostics. The sizing and internal components of a fully shield port plug are shown in Fig. 7 for the midplane port plug and Fig. 8 for an off-midplane port plug. Major materials are B4C (dark gray) and steel (light gray), with the plasma-facing B4C coated in W (green) to reduce the release of carbon via sputtering from C–X neutrals. The inner volume of the midplane port plug is filled via four (A → D) shielding shelves that are installed toroidally and four (A → D) septum trays that are installed radially. Diagnostic components are installed by removing areas of B4C to create voids for transmission of light, routing of cables, or to install components such as mirrors. Diagnostic sub-assemblies can also mount directly to the side plates, the front of which is ∼7 cm beyond the main limiter contour. No components can be mounted to the exterior of the plug to avoid clashing with the port extensions. The main design approach is for port plug clients to only require subtractive manufacturing from the baseline set of port-plug components, e.g., the removal of B4C blocks and the addition of components that require unique hole patterns for assembly. This allows for the parallel fabrication of the main structural components to the point of a common set of blank parts, while the final diagnostic layout and design verification are completed. To avoid neutron streaming, direct lines of sight of the plasma from the air side of the port plug are not used except in key areas where they would compromise the function of the diagnostic, such as for core-viewing vacuum spectroscopy. MCNP modeling has shown that a single 90° dog-leg with length ×2–×3 times the diameter of the void is sufficient. These are generally located within the shielding shelves. All diagnostics that need to transition light or cables through the port flange use standard Conflat-style sub-flanges ranging from DN40 to DN200, with a single instance of a DN250 planned for TSCT. All windows, fiber, and electrical feedthroughs have an interspace that can be gas-backfilled and pumped to mitigate leaks and tritium permeation. These re-makable seal flanges are at the port-plug flange boundary or radially outward. Re-entrant windows are not allowed due to maintainability.
Layout and sizing of a fully shielded midplane port plug for SPARC. Diagnostic systems are integrated by making subtractive modifications to the baseline design by removing shielding blocks and creating tapped holes and voids for mounting components and creating lines of sight.
Layout and sizing of a fully shielded midplane port plug for SPARC. Diagnostic systems are integrated by making subtractive modifications to the baseline design by removing shielding blocks and creating tapped holes and voids for mounting components and creating lines of sight.
Layout and sizing of a fully shielded off-midplane port plug for SPARC. Lower and upper off-midplane port plugs are interchangeable.
Layout and sizing of a fully shielded off-midplane port plug for SPARC. Lower and upper off-midplane port plugs are interchangeable.
The main environmental challenges that in-vessel diagnostic sensors face are high temperatures from flash-heating from disruptions, bake, movement of port plugs during poloidal coil energization, and electromagnetic loads from major disruptions. While the plasma facing end of the port plug will heat to 350 °C during a bake through radiation, the air-side of the flange is maintained via resistive heaters to be at 200 °C, which eases integration of windows and feedthroughs. The flash heating from short, ΔtTQ < 1 ms, thermal quench, mitigated disruptions is a credible risk for components near the front of the port, if left unshielded. The design approach is not to eliminate the risk of flash melting of steel, but to ensure that if it were to occur that any functional component of the diagnostic is shielded by a component that can tolerate the limited melt. One of the early operational challenges of SPARC is to optimize the disruption prediction, avoidance, and mitigation, and the BOLO system incorporates dedicated 3D radiation characterization channels to be used to tune gas fill and timing of the six toroidally and poloidally spaced massive gas injection valves, shown as DMS in Fig. 5.
The out-of-plane force generated by the TF and PF coil interaction and the up/down asymmetries in the load-path from the port-plugs to the building result in small motion of the port plugs relative to Tokamak Hall components. Details are outside the focus of this article, but the net impact is to have positions on the port-plugs move ∼2 mm from the start of a pulse to the start of a flattop. For some diagnostics, this creates ignorable, minor change in the observed field of view, but for long-path length optical systems, this needs to be accounted for in sizing of in-vessel components and real-time control of ex-vessel relay optics. Pointing of lasers and distortion of light collection optics mounted in the septum trays and shielding shelves use port plug displacements when finalizing components.
The MD scenario described in Sec. II is the main structural design driver for diagnostics in both the midplane and off-midplane port plugs. Disruption induced bending stresses and toroidal flowing currents that drive the design in in-vessel components are less in magnitude in the port-plugs. The lower local dBp/dt and lower Bt by allow diagnostic components in the port plugs to grow in size compared to what can fit below the PFCs. The cantilevered design of the port plugs adds an additional 6.7 and 10.0 g vertical acceleration for the midplane and off-midplane ports, respectively. It is possible to expose port-plug mounted components to halo currents if features are far forward on the side plate, resulting in a JxB shear force, but this is very application specific. Overall, sustained design iterations across a wide range of diagnostic sub-systems have resulted in rough finding that structures with linear dimensions above the 200–300 mm range end up being beyond stress allowables.
In contrast to in-vessel diagnostics, it is expected that the SPARC port-based diagnostics will be replaced over time with new and further optimized tools. SPARC presently has no material exchange capability (e.g., DIMES26) or scanning Langmuir probes27 due to the engineering risk they pose in a high-field, D–T environment. Once SPARC operates and uncertainties in the disruption loads are reduced, these standard investigatory tools could be integrated. For similar reasons, for the first generation of port-plugs, SPARC has chosen to not include shutters to cover in-vessel optics. Plasma viewing optics have been collimated and moved radially away from the plasma as much as feasible. There is certainly a risk that SPARC’s wall conditioning (glow-discharge in the absence of TF and ICDC, with or without diborane, while the TF is energized) will accelerate the reduction of reflectivity faster than the irreducible minimum of damage from high-energy, C–X neutrals. The varying design of SPARC’s port-plug based optics will lead to a variety of different risks of coating/erosion. This creates an opportunity where the continual, comprehensive examination of throughput becomes itself a diagnostic and one which can be used to inform future SPARC and ARC optics design.
VI. DIAGNOSTIC LABS
Utilization of the Diagnostic Labs is expected to be open to CFS-funded collaborators or other research teams that contribute equipment through in-kind contributions.3 This makes safety an important consideration, and the system layout and design have been worked to minimize the risk of tritium exposure in the labs. The VCSP spectrometer,23 which must share the vacuum environment with the tokamak, is fully contained in the Tokamak Hall. The XRAY beamlines24 are mechanically continuous through the east wall, but their vacuum environment is isolated from the tokamak with a double-window, He-backfilled interspace. The vacuum vessel reference ground is brought into the Diagnostic Labs for multiple in-vessel diagnostics. This leads to an electrical hazard, which results in the Diagnostic Labs not being able to be occupied during even a H2 SPARC pulse. The design of the shielding blocks to replace the voids shown in Fig. 2 is ongoing. Similar to port-plugs, “dog-legs” are utilized for as many systems as possible and straight through penetrations are minimized in diameter. For both XRAY and neutron diagnostics (NTRN), a direct line of sight is required, and beam stops in the Diagnostic Labs of 1.0–1.5 m have been estimated. In general, the 2.4 m thick concrete wall will provide sufficient shielding to enable sensitive electronics to be placed in the Labs, as up to a 107 reduction in neutron flux relative to the Tokamak Hall is expected. Peaking near penetrations, mitigated with dedicated beam stops, will create zones in the Labs where fluxes are higher, influencing the detailed layout of equipment.
The Lab spaces have basic power and plant services routed to them to support a wide range of diagnostics. Presently, they share up to 240 kW of power, and the waste heat can be removed by chilled water (∼200 kW) and HVAC. The Lab spaces are temperature controlled between 70 and 72 °F with a maximum relatively humidity of 55%. The Tokamak Hall is maintained at a slightly negative pressure relative to the Diagnostic Labs for the purposes of maintaining a known air flow pattern. Gas and compressed air are available to the Labs, but there are no cryogenic feeds, with LN2 available on-site through manual fill and hand-carry. Data systems are presently scoped to handle independent 100 Gb/s links to each of the Diagnostic Labs. Details of SPARC data storage and management of diagnostic data will be the focus of future publications.
A key feature of SPARC is being able to operate in D–T, and a priority of the early campaign diagnostics is to measure Qfus > 1. Sections II, IV, and V have limited mention of neutron diagnostics. This is due to the decoupling between some of the largest design challenges and features of SPARC with those that drive neutron diagnostic design. An overview of the NTRN system is provided in 28, but the important enabling features are the B4C shielding layout in the 0-DEG port opening and the Diagnostic Lab space behind the NC0-NC6 penetrations in the east wall. The 0-DEG port opening in the vacuum vessel is not occupied by a port-plug, but by VV-mounted shielding, adapting design concepts from the septum trays. Also at 0-DEG is where the torus is pumped, which benefits from having as large an opening in the shielding as possible. The shielding has thus been arranged to effectively create a limiting aperture in the 0-DEG port, which enables the tokamak to be used as a pinhole imaging camera to map the neutron emission image onto the east wall vertically over the NC0 slot. This creates a local zone of high directed neutron flux, ∼5 × 1011 n/cm2/s vs the typical, more isotropic and lower energy flux of ∼1 × 1011 n/cm2/s, that can be sampled by a variety of NTRN diagnostics, simultaneously. Toroidally and poloidally away from the 0-DEG midplane port, SPARC is as heavily shielded as possible to avoid overheating magnets. This results in a D–T neutron monitoring approach, which must evolve from concepts developed at JET and TFTR where the nominally toroidally uniform emission source from the plasma was also observable in the Tokamak Hall. SPARC, in essence, has selectively punctured its B4C “blanket” to enable a stream of neutrons to feed diagnostics in a dedicated zone around the central Diagnostic Lab. The plans and challenges for the multiple independent pathways to measure SPARC’s fusion power in support of demonstrating Qfus > 1 will be outlined in future publications.
VII. SUMMARY
Commonwealth Fusion Systems is leading the design and construction of the compact, high-field SPARC tokamak to extend the physics basis for tokamaks and demonstrate a pathway to commercial fusion energy on a timescale that can impact climate change. To achieve these goals in a timely manner, SPARC must be equipped for its early campaigns with sufficient plasma diagnostics to support operations and gain important scientific insights from new regimes. This article outlines the major design drivers ranging from facility-level down to vacuum-vessel and port-plug level. The layout and description of planned diagnostics and their performance function are provided, with the intent on references included here and future publications citing this article as holding the detailed quantitative performance requirements. Details of the vacuum vessel and port-plug integration environment are provided along with features of the Diagnostic Labs. Sufficient details are given within this article to allow for those interested in scoping for future SPARC diagnostics to independently be able to reach early conceptual evaluation.
SUPPLEMENTARY MATERIAL
A full list of the level 1 requirements for the SPARC diagnostic systems is included in the table of the supplementary material. Refer to the text in Sec. III for definitions of the requirement tier and abbreviation of the level 2 system name. The table identifies the function and purpose supported by the diagnostic system as a whole and identified which sub-systems are responsible for performing that function. References included in this publication, as well as future publications, describe how systems are expecting to meet these requirements.
ACKNOWLEDGMENTS
This work was supported by Commonwealth Fusion Systems. The authors thank the broader team that supports the work of the SPARC diagnostic systems. The authors would also like to thank the dozens of experts from institutions around the world who have contributed by being external reviewers on design reviews for the SPARC diagnostics.
AUTHOR DECLARATIONS
Conflict of Interest
All authors are financially supported by Commonwealth Fusion Systems either as employees or through sponsored research contracts. CFS is seeking to commercialize fusion energy and may benefit financially from the science and technologies discussed in this manuscript.
Author Contributions
M.L. Reinke: Conceptualization (equal); Investigation (equal); Supervision (equal); Writing – original draft (equal); Writing – review & editing (equal). I. Abramovic: Conceptualization (supporting); Investigation (supporting). A. Albert: Conceptualization (supporting); Investigation (supporting). K. Asai: Conceptualization (supporting); Investigation (supporting). J. Ball: Conceptualization (supporting); Investigation (supporting). J. Batko: Conceptualization (supporting); Investigation (supporting). J. Brettingen: Project administration (supporting). D. Brunner: Conceptualization (supporting); Funding acquisition (equal); Writing – review & editing (supporting). M. Cario: Conceptualization (supporting); Investigation (supporting). J. Carmichael: Conceptualization (supporting); Investigation (supporting). C. Chrobak: Conceptualization (supporting); Investigation (supporting). A. Creely: Conceptualization (supporting); Investigation (supporting). D. Cykman: Conceptualization (supporting); Investigation (supporting); Supervision (supporting). M. Dalla Rosa: Conceptualization (supporting); Investigation (supporting). E. Dubas: Conceptualization (supporting); Formal analysis (supporting); Investigation (supporting); Supervision (supporting). C. Downey: Conceptualization (supporting); Investigation (supporting). A. Ferrera: Conceptualization (supporting); Investigation (supporting). J. Frenje: Conceptualization (supporting); Formal analysis (supporting); Investigation (supporting). E. Fox-Widdows: Conceptualization (supporting); Investigation (supporting). R. Gocht: Conceptualization (supporting); Investigation (supporting). G. Gorini: Conceptualization (supporting); Investigation (supporting); Supervision (supporting). R. Granetz: Conceptualization (supporting); Investigation (supporting). M. Greenwald: Conceptualization (supporting); Funding acquisition (supporting); Investigation (supporting). A. Grieve: Conceptualization (supporting); Formal analysis (supporting); Investigation (supporting). M. Hanson: Conceptualization (supporting); Investigation (supporting); Supervision (supporting). J. Hawke: Conceptualization (supporting); Investigation (supporting). T. Henderson: Conceptualization (supporting); Funding acquisition (supporting); Investigation (supporting). S. Hicks: Conceptualization (supporting); Formal analysis (supporting); Investigation (supporting). J. Hillesheim: Conceptualization (supporting); Investigation (supporting). A. Hoffmann: Conceptualization (supporting); Investigation (supporting). I. Holmes: Conceptualization (supporting); Investigation (supporting). N. Howard: Conceptualization (supporting); Investigation (supporting). A. Hubbard: Conceptualization (supporting); Investigation (supporting). J.W. Hughes: Conceptualization (supporting); Investigation (supporting). J. Ilagan: Conceptualization (supporting); Investigation (supporting). J. Irby: Conceptualization (supporting); Investigation (supporting). M. Jean: Conceptualization (supporting); Investigation (supporting). G. Kaur: Conceptualization (supporting); Investigation (supporting). R. Kennedy: Conceptualization (supporting); Investigation (supporting); Supervision (supporting). E. Kowalski: Conceptualization (supporting); Investigation (supporting); Writing – review & editing (supporting). A.Q. Kuang: Conceptualization (supporting); Investigation (supporting). R. Kulchy: Conceptualization (supporting); Investigation (supporting). M. LaCapra: Conceptualization (supporting); Investigation (supporting); Supervision (supporting). C. Lafleur: Conceptualization (supporting); Investigation (supporting); Writing – review & editing (supporting). M. Lagieski: Conceptualization (supporting); Investigation (supporting). R. Li: Conceptualization (supporting); Investigation (supporting). Y. Lin: Conceptualization (supporting); Investigation (supporting). T. Looby: Conceptualization (supporting); Investigation (supporting). R. Zubieta Lupo: Conceptualization (supporting); Investigation (supporting). S. Mackie: Conceptualization (supporting); Investigation (supporting). E. Marmar: Conceptualization (supporting); Investigation (supporting); Supervision (supporting). S. McKanas: Conceptualization (supporting); Investigation (supporting). A. Moncada: Conceptualization (supporting); Investigation (supporting). R. Mumgaard: Conceptualization (supporting); Funding acquisition (lead); Investigation (supporting); Supervision (supporting); Writing – review & editing (supporting). C.E. Myers: Conceptualization (supporting); Investigation (supporting); Supervision (supporting). V. Nikolaeva: Conceptualization (supporting); Investigation (supporting). M. Nocente: Conceptualization (supporting); Investigation (supporting). S. Normile: Conceptualization (supporting); Investigation (supporting). C. Novoa: Conceptualization (supporting); Investigation (supporting); Supervision (supporting). S. Ouellet: Conceptualization (supporting); Investigation (supporting). E. Panontin: Conceptualization (supporting); Investigation (supporting). C. Paz-Soldan: Conceptualization (supporting); Investigation (supporting); Supervision (supporting). J. Pentecost: Conceptualization (supporting); Investigation (supporting). C. Perks: Conceptualization (supporting); Investigation (supporting). M. Petruzzo: Conceptualization (supporting); Investigation (supporting). M. Quinn: Conceptualization (supporting); Investigation (supporting); Supervision (supporting). J. Raimond: Conceptualization (supporting); Investigation (supporting). P. Raj: Conceptualization (supporting); Investigation (supporting). M. Rebai: Conceptualization (supporting); Investigation (supporting). V. Riccardo: Conceptualization (supporting); Investigation (supporting); Supervision (supporting). D. Rigamonti: Conceptualization (supporting); Investigation (supporting). J.E. Rice: Conceptualization (supporting); Investigation (supporting); Supervision (supporting). A. Rosenthal: Conceptualization (supporting); Investigation (supporting). M. Safabakhsh: Conceptualization (supporting); Investigation (supporting); Supervision (supporting). A. Saltos: Conceptualization (supporting); Formal analysis (supporting); Investigation (supporting); Supervision (supporting). J. Shanahan: Conceptualization (supporting); Investigation (supporting). M. Silva Sa: Conceptualization (supporting); Investigation (supporting); Supervision (supporting). I. Song: Conceptualization (supporting); Investigation (supporting). J. Souza: Conceptualization (supporting); Investigation (supporting); Methodology (supporting); Supervision (supporting). B. Stein-Lubrano: Conceptualization (supporting); Formal analysis (supporting); Investigation (supporting). I.G. Stewart: Conceptualization (supporting); Investigation (supporting); Methodology (supporting); Supervision (supporting). R. Sweeney: Conceptualization (supporting); Investigation (supporting). M. Tardocchi: Conceptualization (supporting); Investigation (supporting); Supervision (supporting). A. Tinguely: Conceptualization (supporting); Investigation (supporting). D. Vezinet: Conceptualization (supporting); Investigation (supporting); Supervision (supporting). X. Wang: Conceptualization (supporting); Investigation (supporting). J. Witham: Conceptualization (supporting); Investigation (supporting).
DATA AVAILABILITY
The data that support the findings of this study are available from the corresponding author upon reasonable request.