Completion of projects on time becomes a top priority while taking into account the required technical factors. One of the obstacles in the BulakKapal underpass project Bekasi is the soil condition at the project site, which has high compressibility properties such as soft clay. One method to overcome large settlements and accelerate settlement times is to use Pre-Fabricated Vertical Drain (PVD). Thisstudyaimstocomparethedecreaseinsoilconsolidationwithout PVD and by using PVD and knowing excess pore pressure for each variation. Variations used in this study are landfill time, which is 4weeksand8weeksofthe gradual embankment,andthedistanceofPVDis1.2m,1.6m,and2m. These variations are modeled in Plaxis to determine the decrease in consolidation, thevalue ofporepressure, and the acceleration time of consolidation. From the modeling results on Plaxis, it can be seen that the installation distance of PVD significantly influences the time required for the consolidation process. Consolidation settlement using PVD can accelerate the settlement time up to 3.04 times faster than settlement without PVD.
Skip Nav Destination
,
,
Article navigation
21 July 2023
TOWARD ADAPTIVE RESEARCH AND TECHNOLOGY DEVELOPMENT FOR FUTURE LIFE
25–26 October 2021
Palembang, Indonesia
Research Article|
July 21 2023
Acceleration time analysis of consolidation rate using prefabricated vertical drain (PVD) in underpass project completion Available to Purchase
Lolom Evalita Hutabarat;
Lolom Evalita Hutabarat
a)
Department of Civil Engineering, Faculty of Engineering,Universitas Kristen Indonesia (UKI)
, Jakarta Indonesia
a)Corresponding authors: [email protected]
Search for other works by this author on:
Hicca Feby Putri Siahaan;
Hicca Feby Putri Siahaan
b)
Department of Civil Engineering, Faculty of Engineering,Universitas Kristen Indonesia (UKI)
, Jakarta Indonesia
Search for other works by this author on:
Agnes Sri Mulyani
Agnes Sri Mulyani
c)
Department of Civil Engineering, Faculty of Engineering,Universitas Kristen Indonesia (UKI)
, Jakarta Indonesia
Search for other works by this author on:
Lolom Evalita Hutabarat
a)
Hicca Feby Putri Siahaan
b)
Agnes Sri Mulyani
c)
Department of Civil Engineering, Faculty of Engineering,Universitas Kristen Indonesia (UKI)
, Jakarta Indonesia
AIP Conf. Proc. 2689, 040021 (2023)
Citation
Lolom Evalita Hutabarat, Hicca Feby Putri Siahaan, Agnes Sri Mulyani; Acceleration time analysis of consolidation rate using prefabricated vertical drain (PVD) in underpass project completion. AIP Conf. Proc. 21 July 2023; 2689 (1): 040021. https://doi.org/10.1063/5.0114948
Download citation file:
Pay-Per-View Access
$40.00
Sign In
You could not be signed in. Please check your credentials and make sure you have an active account and try again.
30
Views
Citing articles via
The implementation of reflective assessment using Gibbs’ reflective cycle in assessing students’ writing skill
Lala Nurlatifah, Pupung Purnawarman, et al.
Effect of coupling agent type on the self-cleaning and anti-reflective behaviour of advance nanocoating for PV panels application
Taha Tareq Mohammed, Hadia Kadhim Judran, et al.
Classification data mining with Laplacian Smoothing on Naïve Bayes method
Ananda P. Noto, Dewi R. S. Saputro
Related Content
A case study on project performance of railway underpass construction project in Jaipur, India
AIP Conf. Proc. (January 2020)
Traffic and safety characteristics for the Kurdistan Area: Duhok city
AIP Conf. Proc. (September 2023)
Feasibility study of evacuation equipment using the benefit cost ratio bridge duplication project
AIP Conf. Proc. (October 2024)