Construction industry plays an important role in socio-economy development of any developing country. world over, transportation infrastructure projects face delays in commissioning and India is no exception. The time of construction is a benchmark for assessing the project performance. Some of the unexpected activities during project the led to delay in project completion duration. Construction projects delay was considered as the most common problems causing negative effects in the construction projects. In this project we identify the important delay causing factors in the commissioning of metro rail projects in India. In India, several metro rail construction projects experiencing more delays, due to that the initially fixed delivery duration and expenses also exceeded. “delay can be defined as the time overrun or the extension of time for finishing the project”. This paper aims to find out the most significant factors causing delays in Indian metro rail projects through literature review and questionnaire survey. From the literature review 117 causes of delays categorized into 9 different groups, 27 effects were acknowledged and it also rankings given by each authors for the delaying factors aren't an equivalent to varying native and context. Further, the survey is conducted with the participants (contractors, client, consultants and others) of Indian construction. Calculation of relative importance index (rii) for the shortlisted factors yielded the ranking. The ranking by various categories of respondents was analyzed using importance index method (impi%)
Skip Nav Destination
,
,
,
,
Article navigation
19 May 2022
RECENT TRENDS IN SCIENCE AND ENGINEERING
27–28 February 2021
Krishnagiri, India
Research Article|
May 19 2022
Investigation on critical issues of construction delays in Indian metro rail projects
G. Muthamizh Selvan;
G. Muthamizh Selvan
Mahendra Engineering College
, Mallasamudram, Namakkal, India
Search for other works by this author on:
D. S. Kathickraja;
D. S. Kathickraja
Mahendra Engineering College
, Mallasamudram, Namakkal, India
Search for other works by this author on:
P. Dhamodharan;
P. Dhamodharan
a)
Mahendra Engineering College
, Mallasamudram, Namakkal, India
a)Corresponding Author Email: [email protected]
Search for other works by this author on:
P. Saradha;
P. Saradha
Mahendra Engineering College
, Mallasamudram, Namakkal, India
Search for other works by this author on:
V. Shanmugavadivu
V. Shanmugavadivu
Mahendra Engineering College
, Mallasamudram, Namakkal, India
Search for other works by this author on:
G. Muthamizh Selvan
1
D. S. Kathickraja
2
P. Dhamodharan
3,a)
P. Saradha
4
V. Shanmugavadivu
5
Mahendra Engineering College
, Mallasamudram, Namakkal, India
Mahendra Engineering College
, Mallasamudram, Namakkal, India
Mahendra Engineering College
, Mallasamudram, Namakkal, India
Mahendra Engineering College
, Mallasamudram, Namakkal, India
Mahendra Engineering College
, Mallasamudram, Namakkal, India
a)Corresponding Author Email: [email protected]
AIP Conf. Proc. 2393, 020184 (2022)
Citation
G. Muthamizh Selvan, D. S. Kathickraja, P. Dhamodharan, P. Saradha, V. Shanmugavadivu; Investigation on critical issues of construction delays in Indian metro rail projects. AIP Conf. Proc. 19 May 2022; 2393 (1): 020184. https://doi.org/10.1063/5.0087433
Download citation file:
Pay-Per-View Access
$40.00
Sign In
You could not be signed in. Please check your credentials and make sure you have an active account and try again.
49
Views
Citing articles via
Inkjet- and flextrail-printing of silicon polymer-based inks for local passivating contacts
Zohreh Kiaee, Andreas Lösel, et al.
The implementation of reflective assessment using Gibbs’ reflective cycle in assessing students’ writing skill
Lala Nurlatifah, Pupung Purnawarman, et al.
Effect of coupling agent type on the self-cleaning and anti-reflective behaviour of advance nanocoating for PV panels application
Taha Tareq Mohammed, Hadia Kadhim Judran, et al.
Related Content
Need for metro rail system & Its planning using MSP
AIP Conf. Proc. (May 2022)
Key challenges and initiatives undertaken to facilitate BIM adoption in the project: A case of two metro-rail projects
AIP Conf. Proc. (September 2023)
Identification of credible hazards and risk analysis for safety improvement at a metro construction site: A bow-tie analysis approach for your kind consideration
AIP Conf. Proc. (November 2024)
Investigating DDOS attacks on metro network
AIP Conf. Proc. (April 2024)
Research of regenerative braking energy utilization in urban rail transit
AIP Conf. Proc. (January 2019)